No. | Description | Year | Contract No | Period | Contract Price | Remarks |
---|---|---|---|---|---|---|
1 | Refinery Tank Overhaul 216 at Sungai Gerong | 2011 | 233/E13000/2010-SO | 45 Days | Rp. 517.100.000,- | PT. Pertamina UP III Plaju |
2 | Refinery Tank Overhaul 225 Occupaton Sungai Gerong | 2011 | 245/E13000/2010-SO | 45 days | Rp. 968.100.000,- | PT. Pertamina UP III Plaju |
3 | Work Package for EPC Building Work for JCF Demo | 2011 | LOI-JIND-Sekawan-001, dated Januari 21, 2011 | 6 months | Rp. 1.598.000.000 | PT. JGC Indonesia |
4 | New SWS Plant PT. Pertamina (Persero) RU V Balikpapan | 2010 | L-JIND/SK-001, dated Desember 1, 2010 | 180 days | Rp. 13.998.000.000,- | PT. Pertamina RU V Balikpapan |
5 | Construction and Installation Services for 10" Pipeline from BGP to CPS | 2009 | Sp-21144-002-XI-09,dated November, 2009 | 120 Days | US $ 2.288.000 | PT. Meindo Elang Indah |
6 | Replacement Pump-Chemical Injection Pump in UTL-Prod. First Refinery UP. III Plaju | 2009 | 232/E13000/2009-SO | 90 days | Rp. 595.100.000,- & US$ 375.000,- | PT. Pertamina UP III Plaju |
7 | Steel Structure and Piping Work for New LPG Recovery Plant Project. Tuban, East Java | 2008 | No. 3100-201-A, dated 27 May 2008 | 9 months | US $ 3.311.502,00 | PT. Tuban LPG Indonesia |
8 | Painting work for New LPG Recovery Plant Project. Tuban, East Java | 2008 | LOI Sept 15th, 2008 | 6 months | US $ 405.553,50 | PT. Tuban LPG Indonesia |
9 | Piping Work for LPG Tank Project, Tuban, East Java | 2008 | LPG/0806/0049, dated Sept 25, 2008 | 3 months | US $ 285.697,52 | PT. Tuban LPG Indonesia |
10 | PVC Pipe Supply RR S.12,5 = dia 700 MM = 4.698 M' and dia 500 MM = 3.498 M' at Palembang | 2000 | 01/PKK.Pn/PLB/P3P-SS/XI/2000, dated November 01 2000 | 3 months | Rp. 28.000.000.000,- | SNVT PKPAM Prov. Sumatera Sumatera |